6.1 Development will not be permitted where it would:

  1. Be at risk of flooding and no appropriate flood alleviation measures exist or will be provided by the developer, AND/OR
  2. Increase the risk of flooding elsewhere by reducing the capacity of the floodplain, installing a culvert, or increasing the flow of water into the floodplain, AND/OR
  3. Harm existing flood defences or have an impact on proposed flood defence schemes, AND/OR
  4. Restrict adequate access to the river and/or existing flood defences for routine maintenance and improvement.

6.2 Appropriate flood alleviation measures may include the use of Sustainable Urban Drainage Systems (SuDS). However any measure would have to first be approved by the Council and the Environment Agency.

6.3 Proposals for development within areas liable to flood8 must be accompanied by an appropriate9 Flood Risk Assessment where the development is perceived10 to be at risk of flooding or the development is likely to increase the risk of flooding elsewhere.

View this result in context

Disclaimer: Every effort has been made to ensure that the electronic version of the Replacement Pendle Local Plan 2001-2016 is as accurate as possible. However, in some instances, the appearance of the Proposals Map online may differ slightly from the paper version due to issues with electronic displays. If users are in any doubt about the content of the Proposals Map please verify the information by referring to the published paper edition as this represents the definitive version of the Local Plan.